Week 14

In this final week, we spent most of the time working on our final presentation as well as getting our build…

Week 13

We had our softs presentation this week and we received an overall positive feedback on our…

Week 12

We started working on the changes that we decided to implement before Softs next week. We also got…

Week 11

We got finished with Playtest Day this Saturday with a positive response from our players…

Week 10

We worked on adding more gameplay elements and enemies to our level as per the feedback…

Week 9

This week, two of our teammates were off for GDC and we kept working on making new acts…

Week 8

We came back from Spring Break ready to continue on our level. This week we made a lot of changes…

Week 7

We presented our progress, vision and direction this week during our halves presentation. We worked…

Week 6

We started work on the blockout for Act 4 of our level and also started preparing for our halves…

Week 5

We had our team bonding dinner and our first playtest this week and we received really good…

Week 4

We completed our golden spike, finalized our game mechanics and theme and in between …

Week 3

We completed our golden spike, finalized our game mechanics and theme and in between …

Week 2

We had our first meeting with our SME this week and the rest of the week was spent in working on…

Week 1

The first week was getting to know about each other, the instructors and to decide what everyone…